MAN 4504 PROJECT 2 GUIDELINES |
LAST UPDATED: Monday February 11, 2008 10:38:04 PM -0500 |
|
You need to bring a hard copy to class and email me as well.
Your paper should include the following:
Page 1
Title of paper
Student Name
Student course number and course name
Semester and year
Name of University
Name of Professor - correctly spelled
Visible digital photo of yourself
2. Page 2 Table of contents
3. Pages 3 - 5 Your answers to Problem Assigned ( it is up to you on how many pages you place your answers)
Paper should be |
|
Project 2 Topic
A partially solved PERT problem is detailed in the table below. Times are given in weeks. You need to show your work!
Activity |
Preceding |
Optimistic Time |
Probable Time |
Pessimistic Time |
Expected Time |
Variance |
A |
-- |
7 |
9 |
14 |
|
1.361 |
B |
A |
2 |
2 |
8 |
|
1.00 |
C |
A |
8 |
12 |
16 |
|
1.778 |
D |
A |
3 |
5 |
10 |
|
1.361 |
E |
B |
4 |
6 |
8 |
|
0.444 |
F |
B |
6 |
8 |
10 |
|
0.444 |
G |
C, F |
2 |
3 |
4 |
|
0.111 |
H |
D |
2 |
2 |
8 |
|
1.000 |
I |
H |
6 |
8 |
16 |
|
2.778 |
J |
G, I |
4 |
6 |
14 |
|
2.778 |
K |
E, J |
2 |
2 |
5 |
|
0.250 |
a. Calculate the expected time for each activity. Enter these values in the appropriate column in the table above.
b. Which activities form the critical path?
c. What is the estimated time of the critical path?
d. What are the project variance and the project standard deviation?