PERT Exc.

 

Using Microsoft Visio please create a PERT chart based on the information below:

(You will need to determine slack and CP as well).

 

Activity

Duration (Weeks)

Preceding Activity

A.  Obtain Approval

2

None

B.  Assign Tasks

2

A

C.  Send memos and emails

1

A

D.  Form Committee

3

A

E.  Select Software

3

C,D

F.  Arrange Rooms

1

D

G.  Train Group 1

5

B

H.  Prepare Policies

3

D

I. Draft Manuals

3

G

J. Review, approve, and make copies

6

A

K.  Review Documentation

10

J,E,F,H,I

L.  Distribute in all departments

1

K